pcusa.gif (2519 bytes)   Task Force Updatespcusa.gif (2519 bytes)

First Presbyterian Church of Freehold, 118 West Main Street, Freehold, NJ

Home
Up

 

BUILDING TASK FORCE UPDATE

 

September 2006 Update

Sunday, September 10 was a wonderful day at First Presbyterian Church of Freehold! During our morning worship service we dedicated our renovated and restored facilities to be used for Christ’s ministry. The Rev. Bill Jordan, Executive Presbyter of Monmouth Presbytery preached, challenging us to build on the rock of our faith. We also recognized the contractors and local officials who were celebrating with us. This project, however, would not have gotten off of the ground without someone with vision and energy to lead the way. Special thanks was given to Bev Dame and Bill Reid who co-chair the Building Task Force. Other members of the task force include: Ruth Buffett, Lori McCoy, Fred Scott and Derek Munnery.

After the service, a reception was held and the buildings were open to take a look at the renovations. More work must be done to complete the project – the most important of which is the installation of additional electrical power; this is scheduled to be done the week of October 2. Once the additional power is available, the elevator and several other small tasks will be completed and we should be able to use all of our facilities; we’re hoping this takes place by the end of October.

We are extremely grateful to the many people who have given of their time and energy to see this project come about, and especially to those who spent their Saturday mornings in late August and early September moving furniture and other items into the renovated spaces.

Once the project is completed, our mortgage will begin. We will need you to continue your generosity to this project.  In the meantime, stop by the church and take a look at the new church offices and the handicapped bathroom in the auditorium.

The work which has been done in the rear of the sanctuary building can only be viewed on Sunday mornings until we receive our Certificate of Occupancy. Thanks be to God for this Journey of Faith.

 

August 2006 Update

As the Building renovation and restoration project nears completion, we are preparing for our Service of Dedication on Sunday, September 10 at 9:30am. In the meantime, work continues .  By Mid-August:

bullet

The church offices were completed

bullet

The music office on the Second floor of the Sanctuary Building was being finished.

bullet

Painting and flooring/carpeting were being completed.

bullet

The Air Conditioning for the sanctuary was nearly operable, but waiting for JCP&L to provide more electricity to the church, without which the Air Conditioning cannot be run.

bullet

Folding partitions were being installed in the upstairs of the Christian Education Building and in the first floor of the Sanctuary building

bullet

The Bathroom in the Auditorium was nearing completion

bullet

The new handicapped ramp was being finished and sidewalks poured

bullet

The last two major items to be completed will be the installation of the elevator in the Sanctuary building and the chair lift in the Christian Ed building.

 

Please join us on September 10 to celebrate your patience, the hard work of the Task Force, and the new possibilities for ministry our expanded facilities will offer. Tours will be available to see the work - which should all be completed by then!  If you have any questions, please contact any member of the task force:

Bill Reid, co-chair                    Bev Dame, co-chair

Lori McCoy                               Ruth Buffett

Derek Munnery                         Fred Scott

 

July 2006 Update

 

bullet

 New electrical service to the facility will be switched over by the first week of July

bullet

The onsite storage trailer has been emptied, with the contents being moved to the auditorium

bullet

 Spackling and taping of the drywall has begun; walls will be painted in mid-July.

bullet

 Flooring should be installed by the end of July  

bullet

Save Sunday, September 10 on your calendar. That will be a very special day as we Dedicate our new facilities!  Join us at 9:30am for a worship service which will include special music and guest preacher, The Rev. Dr. Bill Jordan, Executive Presbyter of Monmouth Presbytery. Following the service there will be a special reception and the opportunity to tour the renovated areas. We expect local dignitaries and other members of the community to be with us for this celebration.

Questions: Contact Bill Reid or Bev Dame

 

 

June 2006 Update

 

bullet

The Renovation and Construction Dedication Service has been postponed until Sunday, September 10 because of a delay in the production of the elevator for the sanctuary building.

bullet

The air conditional units and the main branches of ductwork are installed in the sanctuary.

bullet

Work is continuing on the electrical and plumbing updating.

bullet

The chair lift has been ordered for the Christian Ed. Building.

bullet

Carpeting has been ordered.

bullet

Currently over $435,000 has been received from member pledges and donations.  We anticipate the total cost of the project to be ~$1.3 million.  We continue to be extremely grateful for your contributions toward the Capital Improvement Campaign/Journey of Faith.  Please make sure your donations are marked either “CIF” or “BTF”.

bullet

We anticipate the project being completed by August.

bullet

The storage trailer will be unpacked at the end of June.

     Bill Reid and Bev Dame, Co-Chairs of Building Task Force

 

 

May 2006 Update

 

bullet

Our “Journey of Faith” continues along, with completion set for mid to late June.

bullet

 Mark your calendars for Sunday, June 18.  That morning we will have a special service of dedication, during the 9:30am worship hour.  Special music, special guests, and a special preacher - Dave Watermulder!  Come join us as we thank God for God’s blessings to our congregation.

bullet

 Though you may not see anything happening, much work is being done in the sanctuary building to install the air conditioning.  Vents are being installed, ductwork is being laid and the condenser is being built.

bullet

 We continue to be grateful for your donations and pledges.  To date, over $450,000 has been received, toward the estimated $1.3 million cost.  Of the monies received, we have had to pay for the architect and fundraising consultant, in addition to construction costs.  Your continued generosity is needed.  Please make sure that all of your donations are earmarked “CIF” - Capital Improvement Fun.

 Bill Reid and Bev Dame, Co-Chairs

 

April 2006 Update

 

bullet

The masonry work for the elevator shaft in the Sanctuary building is completed.

bullet

The walls of the auditorium bathroom have been installed, as have the walls in the church office and in the rear of the Sanctuary building.

bullet

Electrical and plumbing work has begun in several parts of the project.

bullet

The second stairway in the rear of the Sanctuary building has been installed.

bullet

Tours were given on Sunday, March 26 to all who were in Sunday School or at Worship.

bullet

Over $400,000 has been received from pledges and donations toward the completion of the project; total cost including architect and capital campaign fees is $1.3 million.  We also have received donations of new desks for the Pastors’ offices and a new office computer.  If you are not using capital campaign envelopes to make your contribution, please make sure that your donation is clearly marked “CAPITAL CAMPAIGN FUND”.

bullet

The project is on schedule at this time.

 

 

March 2006 Update

 

bullet

The project is running on schedule, if not a little ahead due to the warm January weather.

bullet

A meeting was held on January 19 with members who had joined  the church since the Campaign began in April 2004.

bullet

Currently, work is being done to prepare the attic of the Sanctuary building for the installation of the air conditioning.  Also, the second stairway has been added to the rear of the sanctuary building, and the elevator shaft is in the process of being built.

bullet

In the Christian Ed. Building, the offices have been sheetrocked.

bullet

Outside, the porch and ramp are in process; once the weather becomes warmer, the ramp will be covered with stone, matching the building.

bullet

A REMINDER: Please do not open the fence and walk through the construction area between the two buildings.  Also, do not go into the rear of the sanctuary building.  Some time in the next month, we will be having tours and a construction update for the congregation.  Look in the bulletin for more information.

bullet

We still encourage you to remember to be generous to the Capital Campaign Fund!  Your generosity is very important to us as we continue the construction phase.  We are grateful for your participation in the Proceeds night at TGIFriday’s; we receive an average of $120 from each gathering.  Also, thank you for turning in your ACME receipts.  So far, we have received nearly $400 toward our project from your receipts.  REMINDER: the PINK ENVELOPES IN YOUR OFFERING ENVELOPE BOX ARE NOT FOR THE CAPITAL CAMPAIGN; PLEASE USE CAPITAL CAMPAIGN ENVELOPES TO MAKE YOUR DONATIONS.

bullet

We covet your prayers as we move forward in our “Journey of Faith”. 

                    Bill Reid and  Bev Dame, co-chairs

 

 

February 2006 Update

bullet

1.  Progress continues to be made on our renovations.  Starting the week of December 12, our contractors began the process of renovating walls in the rear of the Sanctuary building and the CE building, digging the elevator shaft, removing the wooden ramp at the rear of the Sanctuary building, building the new ramp and porch off the rear side of the Sanctuary, and the additional stair case is being built for the Sanctuary building.

bullet

2.  We continue to be grateful for the financial support of the congregation.  Over $30,000.00 in ACME grocery receipts have been turned in- keep them coming;  the Capital Campaign receives 2% of the total receipts.  Also, TGIF Proceeds Night continues to bring in between $120 and $180 per time.  Our next Proceeds Night is Thursday, February 16th.  Don't forget, Dottie Burdge's Bread & Butter  Pickle proceeds also go to the Capital Campaign Fund.  Finally, we encourage you to keep your pledges to the Capital Campaign up-to-date.  Nearly $400,000 has been given so far; the final cost of our project, however, is $1.3 million.  The more funds we have on hand prior to the end of construction, the lower our mortgage payment will be.

bullet

3.  We are pleased, given the age of our building, that we have not encountered too many difficulties.  The only significant add-on we had is to re-enforce the foundation in the basement where the elevator shaft was being dug.  This will cost us an additional $15,000.00.

bullet

4.  Please check the church website periodically for photo updates of the project.  The website address is:  www.monmouth.com/~fpcf .  If you do not have access to the internet, copies of the pictures are available in the church office.

bullet

5.  Reminder:  Please do not go into the rear of the Sanctuary Building!  Later in March, tours will be offered.

 

 

December 2005 Update

bullet

As we prepare for the Holidays, you will begin to see construction activity around the church. As of 11/15/05 permits were being obtained from Freehold Borough to begin our work. We are extremely grateful to Mayor Wilson and the Freehold Borough Council who adopted a resolution waiving all of our permit fees.

bullet

As work progresses we will keep you informed of any inconveniences you may experience. We are grateful for your patience and cooperation as we undergo this much needed project.

 

 

November 2005 Update

bullet

After receiving and reviewing bids from 7 contractors, a contract will soon be signed with Charles B. Hembling & Sons of Shrewsbury to be our general contractor. Once the contract is signed, work will begin.

bullet

The cost of the project is $1.13 million, which includes air conditioning for the Sanctuary, renovations to the rear of the sanctuary building, with an elevator installed, a bathroom in the auditorium and the creation of new church offices.

bullet

To cover the project, a construction loan of up to $900,000 has been secured from First Washington Bank and has been approved by Monmouth Presbytery.

bullet

Currently there is over $180,000 in the Capital Campaign account; to date over $350,000 has been received. Monies have been paid to the architect and to the Capital Campaign fundraiser. Thank you for your generosity. If you have not donated to the fund, please talk with Polly Hartzell about how to do so.

 

 

October 2005 Update

bullet

A loan has been secured from First Washington Bank.

bullet

Monmouth Presbytery has given us the final approval to go ahead with our loan and project.

bullet

Seven Contractors participated in a walk through of the intended renovations. Bids have been received from 5 Contractors and are being reviewed by the Architect. Contractors will then be interviewed by the Task Force Co-Chairs.

bullet

Donations continue to be received, with over $177,000 on hand at the present time.

bullet

In July and August, $8600 was received for the Capital Improvement Fund from member donations.

bullet

Plans are on schedule for a mid-October start to the renovations.

For more information, please contact either Bill Reid or Bev Dame.

 

 

September 2005 Update

bullet

As of July 31, 2005, there was $180,438 available in the Capital Improvement Fund. Monies have been paid so far to the Architect and to the Capital Campaign consultants.

bullet

Loan offers from First Washington Bank and PNC are currently being considered.

bullet

On August 13, everything from the back of the Sanctuary building was moved either to the Auditorium or to the Storage trailer which is in the rear parking lot. If you have items which were in that location, please contact the church office to find out where they have been stored.

bullet

Because the auditorium is being used for storage, for all of the music, and for Sunday School, most large group activities for the coming year will be postponed. If you have planned a group meeting for the auditorium, please check with the Building Task Force to see if your meeting is possible.

bullet

Bids for the construction are due in by August 31, at which time the winning bids will be selected. Construction should begin in early September.

bullet

We ask for your prayers as well as your patience in the coming months during this period of renovation and restoration. Flexibility will be the key!

If you have any questions, please contact any member of the task force:

Bill Reid, co-chair

Bev Dame, co-chair

Ruth Buffett

Peter Ciok

Lori McCoy

Derek Munnery

Fred Scott

 

 

July 2005 Update

bullet

Contributions continue to come in. At the end of May, total contributions reached $314,835. This includes over $700 which has been raised through the benefit nights at TGIFridays.

bullet

Members of the task force have been meeting with banks regarding a mortgage. They have met with Freehold Savings, PNC and First Washington.

bullet

At their May meeting, The Presbytery of Monmouth approved our plans to continue with our project.

bullet

In early July Eric Holtermann, our architect, will meet with the task force for a final look at the plans before they are sent to be bid on by general contractors.

bullet

Fred Scott and Derek Munnery have joined the Task Force as of the July Meeting.

bullet

Plans are being made to begin to prepare our buildings for construction, which is tentatively planned to begin in September. The Nursery has already been moved to Room 8 on the Second Floor of the Christian Education Building.

Questions: Contact Bill Reid at 732-928-9367 or Bev Dame at 732-446-0314

 

 

June 2005 Update

bullet

The Capital Improvement fund received $9, 688 during April, bringing the amount on hand to $309,555.

bullet

Several members of the Building Task Force have been meeting with representatives of local Financial Institutions to talk about obtaining a line of credit/mortgage.

bullet

The Building Task Force will be meeting with Eric Holtermann, the architect in early June to look at the detailed plans.

bullet

At the end of the Sunday School year, the Church nursery will be moved to the 2nd floor of the Christian Education Building to make way for Sunshine Schoolhouse to move the items they have stored in the Rear of the Sancutary building.

bullet

Construction is tentatively scheduled to being in early fall.


If you have questions, please feel free to contact Bill Reid or Bev Dame, Building Task Force Co-Chairs.

 

 

 

May 2005 Update

Our plans for the renovations of our facilities is moving right along.  In the past month, Monmouth Presbytery's Council has recommended approval of our mortage to assist with the costs of our plan.  At this point it looks like the total cost of the renovations of the rear of the sanctuary building, the minor changes to the second floor of the CE building, the bathroom on the Auditorium level and the air conditioning of the sanctuary building will be around $1.2 million dollars.  The architect, Eric Holtermann, is now working on specific details of the plan so that bids can be sought.  Construction should begin this summer.

Our Capital Campaign continues to move along well. The total donated as of April 17 is $306,006.  If you haven't pledged toward the Capital Campaign and would like to do so, please contact Polly Hartzell at 732-901-8946.  We are grateful for your generosity.  Additional ways to contribute to the fund are by attending the TGIFriday's Proceed night, purchasing AMWAY products from Colin Lancaster, and participating in the BARGAIN BAZAAR on June 18.

If you have questions about the Building Campaign, please talk with a member of our Task Force listed below.  Look for more frequent updates coming your way!

Bill Reid and Bev Dame, Co-Chairs; Ruth Buffet, Peter Ciok, Lori McCoy, Cathy Gallene.  Pastor David serves as ex-officio.